Full-staging falsework for a deck cast in place: plywood on H20 joists, steel primary beams along the bridge, twin cap beams across, and steel pipe shores braced every 4 m on pads. Set a road underneath and the scheme changes: long beams span a traffic opening on shore towers either side, with barriers, a crash deck and night closures, and the tool prices the alternative of diverting the road. A concept sketch, not for construction.

Designing…
Most falsework trouble starts at the bottom: pads on soft or wet ground settle unevenly, so check the ground and keep water away from it. Over a live road the dangerous moments are erecting and removing the long beams; plan the night closures first. Set the forms with camber for the beam deflection, and strike in the order the designer gives.
Inputs are saved on this device · reset to defaults
Loads follow falsework practice: wet concrete at 25.9 kN/m³ with its reinforcement, 0.5 kPa for the forms and 1.0 kPa of construction live load, never less than 4.8 kPa in total, factored 1.25 on the dead load and 1.5 on the live load; horizontally the larger of 2 % of the dead load and the wind. Under the webs of a box or the ribs of a T-beam the concrete is concentrated, so the worst primary beam carries 1.6 to 1.8 times the average, and across a box the cap beams and shores near the webs carry more than the others.
H20 joists are checked against their permissible moment and shear; the steel primary beams, cap beams, opening beams and transfer beams and the pipe shores to AISC 360-16 (the same member functions as the Trestle tool). Beams that carry wet concrete deflect no more than span / 240. Shores carry axial load with a 25 mm eccentricity at the jack and are braced every 4 m both ways; pads are sized for the ground you choose.
With a road underneath, the opening beams, the transfer beams, the tower shores (150 % of their load next to traffic, plus a tie force), the headroom, barriers, crash deck, lighting, the temporary works design check, traffic management and night closures are added, and the same deck is priced again with the road diverted. The same engine prices the falsework of cast-in-place decks in Bridge Design. Related: full-staging method, falsework design, trestle, wind load.
A temporary support that carries the formwork and the wet concrete of a deck cast in place until the deck can carry itself (after stressing for a prestressed box). Here it is steel pipe shores on pads, twin cap beams across the bridge, steel primary beams along it, H20 timber joists and plywood.
The shores stop either side of the road behind temporary concrete barriers, and long steel beams (deep H-beams or welded plate girders) span the traffic opening on towers of shores. The beams go up and come down in night closures, a crash deck under them catches anything dropped, and the posts next to traffic are designed for one and a half times their load.
Whatever the road authority sets for temporary works; 5.5 m is common for temporary structures over roads in the Gulf. The tool checks the underside of the long beams against the clearance you set and warns when the beams are too deep.
It depends on the deck weight, the height and the beams on top. The tool designs every grid from 1.5 to 6 m along and 1.5 to 4 m across and keeps the cheapest; heavy box girders usually end up on 3 to 6 m by 3 to 4 m grids with steel primary beams.
Sometimes. A diversion removes the long beams, towers, barriers and night closures, but costs a temporary road and its upkeep. The tool prices both and shows the alternative next to the chosen one.