FCM box-girder sizing

Free-cantilever-method PSC box girder, three-span continuous. Drag the main span and the side-span ratio — the elevation, depths and proportioning checks update live against typical built-bridge bands. A first-sizing aid for layout, not a code check.

Girder section at pier
Girder depth
H pier  0.055L + 0.546
H mid  0.022L + 0.626
Main span150m
50125200
Side-span ratio×0.60
0.500.600.70
#CheckFormulaValueTypical bandStatus
Bands: L/H pier 18–22 (opt. 20), L/H mid 35–50 (opt. 45), L side/L main 0.60–0.70 — international practice ranges for variable-depth segmental box girders (ASBI / PCI, ASPIRE). The depth formulas give a starting section: below a band means the section is deeper than typical (stockier, conservative); above a band means more slender, worth a closer look. Note these formulas are dimensional (metres only) and are a layout starting point — final sections must pass full strength, service and construction-stage checks.
Field notes — what to watch for

The pier-table depth-to-span and midspan depth-to-span ratios here are the ones owners' engineers check first in review — land inside them and the conversation is easier. Remember the governing case for the pier is often during construction, one segment out of balance, not the finished bridge.

Inputs are saved on this device · reset to defaults