Also called: AS method, spinning wheel, wire-by-wire cable erection
How it is done
- Hang the catwalk and a hauling rope; load wire reels at one anchorage.
- The spinning wheel carries a bight of wire across, looping around the strand shoe at the far anchorage; the wire is adjusted to the correct sag on each pass.
- Form each strand of 100-500 wires, band it, and place it in the saddles; when all strands are in, compact the cable with a hydraulic compactor to a circular section and install cable bands.
- Wrap with wire or a polymer sheath and dehumidify.
Where it fits
- Very long spans (over 1,500 m) where prefabricated strands become too heavy to handle; sites with the crew skill.
Where it does not
- Spans where PPWS is faster and cheaper (most modern spans below 1,500 m).
Plant, pace and money
PlantSpinning wheels and tramway, catwalk, adjustment gantries, compactors.
ProductivityMonths; the Akashi Kaikyo cable took about a year with PPWS after trials.
CostCable USD 8,000-15,000 per tonne installed.
Risks and controls
What goes wrong
- Wire sag errors, wire breaks, weather stoppages, wire corrosion before wrapping.
Quality assurance
Sag adjustment of every strand relative to a reference strand, wire counts, compaction diameter checks.
Examples
Golden Gate, Verrazzano, Humber, Great Belt East, Storebaelt; Chinese Xihoumen used PPWS.