A crane is only as safe as the ground under it. This tool finds the load under the worst track of a crawler crane or the worst outrigger of a mobile crane, compares it with what the ground can carry, and then picks the cheapest way to make it work: crane mats in timber or steel, a working platform of crushed rock, or both. A concept sketch, not for construction.
Designing…
Walk the pad before the crane arrives. Look for backfilled trenches, manholes, soft spots after rain and the edge of any excavation: ground that carries the load in the middle of the site may not carry it one metre from a trench. Lay the mats level and tight together, centre the outrigger plate on them, and watch the first lift for any sinking.
Inputs are saved on this device · reset to defaults
Loads first. The lifted load is taken with a 1.15 hoisting factor. For a crawler crane the resultant moves towards the tipping line in proportion to the use of the load chart (rated loads are 75 % of tipping), and the most loaded track is found for a lift over the side, over the end and over a corner. For a mobile crane the worst outrigger takes a quarter of the weight plus the load moment on the outrigger base at the worst slew angle. The crane classes are generic: type the real weight, base and loads when you have them.
Then the ground. The ultimate bearing pressure of a surface footing comes from the undrained strength of a clay (5.14 cu with a shape factor) or the friction angle of a sand (0.5 γ B Nγ with a shape factor, about halved by a water table at the surface), divided by a factor of safety of 2 unless you change it. A track loaded off-centre is counted only over the length centred on the resultant. If you know the allowable bearing pressure, type it and it replaces the estimate.
Then the fix. Bare ground, one layer of mats, two crossed layers, and each of those on a platform from 0.3 to 1.5 m thick are all checked, and the cheapest that works is kept, with the others listed beside it. The same engine is in the Temporary works panel of Bridge Design. Related: trestle, temporary bents, spread footing, pile capacity.
The prepared ground a crane stands on while it lifts: crane mats, a layer of compacted crushed rock, or both, sized so that the pressure reaching the natural ground is less than it can carry. Many crane accidents start with an outrigger or a track sinking into ground that looked firm.
The reliable source is the crane maker: most give outrigger loads for a planned lift. Without that, a common estimate takes a quarter of the total weight on each outrigger and adds the share of the load moment, with the boom slewed to the worst angle over one outrigger. This tool uses that estimate and lets you type the maker’s figure over it.
The crane and its load act as one resultant that moves towards the tipping line as the lift uses more of the load chart. Over the side, the near track takes most of the load; over the end, both tracks are loaded towards one end, in a trapezoid or a triangle. The tool checks the side, the end and a corner, and uses the worst.
Big enough that the pressure under them is less than the allowable bearing pressure, but a mat only spreads load as far as it is strong and stiff enough to do so. The tool treats the mat as a beam on a uniform reaction, checks bending and shear, and counts the mat no further than a few thicknesses beyond the plate or track. Two crossed layers spread the load both ways.
When mats alone cannot bring the pressure down to what a soft ground can carry, or when the crane has to travel. A layer of compacted crushed rock spreads the load over a larger area of the ground beneath it. The tool spreads the load at 1 horizontal to 2 vertical and checks both the platform under the mats and the ground under the platform.