Also called: jacket pier, jacket foundation, template foundation, offshore jacket, pile-supported jacket platform
How it is done
- Design for waves, current, ship impact, earthquake and fatigue at the tubular joints; choose the number of legs, the pile layout and the connection (piles through the legs or skirt piles in sleeves).
- Survey the seabed and clear obstructions; place a scour filter layer, and design mudmats to carry the jacket on the bed before it is piled.
- Fabricate the jacket in a yard: weld the tubular nodes, inspect them by ultrasonic and magnetic-particle testing, fit anodes, grout lines and lifting points, and load out onto a barge.
- Transport to site and set the jacket on the seabed with a floating or jack-up crane, levelling it on its mudmats within tolerance.
- Drive the piles through the legs or sleeves (or pre-drive them through a template and set the jacket over them), checking inclination and refusal; drill out if refusal comes early.
- Grout the pile-to-sleeve or pile-to-leg annulus and check grout returns and cubes; alternatively weld or swage the connection.
- Install the pier cap, deck supports or transition piece, complete splash-zone corrosion protection, and set up inspection of joints, anodes and scour.
Key numbers
- Water depthabout 10–40 m for bridge and airport structures; offshore oil jackets to about 400 m (Bullwinkle, 412 m)
- Pilessteel pipes of about 1.0–2.5 m, driven or drilled and grouted
- Leg batterabout 1:7 to 1:10 in offshore practice
- Minimum pile wall (API)6.35 mm + D/100, thicker where driving stresses or bending govern
- Jacket massa few hundred to a few thousand tonnes for bridge-scale units, set in one lift
Where it fits
- Marine viaducts, approach structures and pile-supported platforms in about 10–40 m of water, soft or variable seabeds, exposed sites with short weather windows, and projects with a fabrication yard and heavy-lift vessels within reach.
Where it does not
- Piers exposed to large ship impact without separate protection.
- Rivers with heavy debris or ice that would load and damage slender members.
- Owners who cannot maintain splash-zone coatings and cathodic protection over the design life.
Choosing it
- Choose a jacket over a pile group with a cast-in-place cap where water is deep, the seabed soft or the site exposed, and a yard can build repetitive units; offshore work shrinks to setting and piling.
- Choose it where the structure must not obstruct water flow; at Haneda the D Runway crosses a river outflow on a jacket-supported pier rather than on reclaimed land.
- Prefer large-diameter monopiles, or bored piles with precast caps, in moderate water depths, where a jacket's fatigue-sensitive joints and corrosion protection would add maintenance.
- Prefer gravity bases or caissons for pylons exposed to ship impact; a jacket is stiff, but its slender members are vulnerable to collision.
Plant, pace and money
PlantFabrication yard with tubular welding and NDT, transport barges, floating crane or heavy-lift vessel of about 1,000–5,000 t, hydraulic impact hammer with followers, drilling spread for refusal, grout plant, divers or ROVs.
ProductivityFabrication runs in parallel with seabed work; at sea a jacket is set in about a day in suitable weather and piled and grouted in about one to two weeks.
CostIndicative: fabricated jacket steel USD 4,000–10,000 per tonne; a bridge-scale jacket with its piles about USD 3–15 million per pier, depending on water depth, steel weight and marine spread.
Risks and controls
What goes wrong
- Fatigue cracking at tubular joints under waves and traffic.
- Splash-zone corrosion and anode depletion.
- Pile refusal or misalignment in the sleeves, and poor grout in the annulus.
- Vessel collision with slender members; scour undermining the mudmats.
Quality assurance
Weld procedure qualification and NDT records for every node, dimensional survey before load-out, seabed and setting surveys, pile-driving records and inclination, grout cube strengths and return checks, cathodic-protection potential surveys and periodic underwater inspection.
Origins
Steel jackets evolved from the template platforms of the Gulf of Mexico after 1947 and reached 412 m of water with Bullwinkle in 1988; offshore wind adopted them for deeper sites with the Beatrice demonstrator (2006), and Japan placed the pile-supported section and taxiway bridges of Haneda Airport's D Runway (2010) on steel jackets.
Examples
Thousands of offshore oil and gas platforms since the late 1940s, jacket-founded offshore wind turbines in deeper water, and the jacket-supported pier section and connecting taxiway bridges of Haneda Airport's D Runway in Tokyo Bay.
Case studies
Haneda Airport D Runway, TokyoJapan · 2010Hybrid runway of reclaimed land and a pile-supported section on steel jackets where it crosses the Tama River outflow; the connecting taxiway bridges are also founded on jackets.
Bullwinkle platform, Gulf of MexicoUSA · 1988Fixed steel jacket in 412 m of water, the deepest of its kind when installed.
Beatrice offshore wind demonstratorUK · 2006–07Two 5 MW turbines on jackets in about 45 m of water off Scotland, an early demonstration of jackets for deep-water offshore wind.
Related methods
Further reading
ISO 19902 Fixed steel offshore structures · API RP 2A-WSD Planning, Designing and Constructing Fixed Offshore Platforms · DNV-ST-0126 Support structures for wind turbines · Gerwick, Construction of Marine and Offshore Structures