Also called: panel formwork, lift-by-lift pier construction, gang forms
How it is done
- Cast a starter with the footing; fix the reinforcement cage for the first lift with couplers or laps for the next.
- Set the formwork on the starter, plumb and brace it; pour with a pump; strip after a day and cure.
- Lift the forms to the next lift; the pier head or hammerhead is formed on a shored platform or a bracket system.
Where it fits
- Piers up to 15-25 m in numbers of 10-40 on a viaduct; any shape the formwork can be built for.
Where it does not
- Tall piers where each crane lift costs a day; use climbing forms above about 25 m.
Plant, pace and money
PlantFormwork sets (two or three in rotation), crane, concrete pump, access scaffold.
ProductivityA lift every three to five days per set; a 15 m pier in two to three weeks.
CostUSD 400-700 per m3 of pier concrete in place.
Risks and controls
What goes wrong
- Formwork blowouts, cold joints, cover loss at lift joints, falls from height.
Quality assurance
Plumbness surveyed every lift, cover meter checks, cube tests, joint preparation between lifts.
Examples
The default pier construction in the game's schedule for piers under 15 m.
Related methods
Further reading
ACI 347 Formwork · CIRIA C716