Also called: hammerhead cap, pier cap construction, cantilever pier head
How it is done
- Cast the column to the soffit level; install bracket frames bolted through the column or a shored platform from the ground.
- Fix the reinforcement and post-tensioning ducts, form the head, pour in one operation, cure, stress the tendons, strip.
- Set bearing plinths to level with a laser survey; grout the bearings.
Where it fits
- Every pier with bearings; hammerheads for single columns under 12-25 m wide decks; multi-column caps on wide urban viaducts.
Where it does not
- Over-wide hammerheads without post-tensioning; brackets on slender columns without a check.
Plant, pace and money
PlantBracket system or falsework, crane, stressing jacks.
ProductivityTwo to three weeks per head.
CostUSD 600-1,000 per m3, higher than the column.
Risks and controls
What goes wrong
- Bracket collapse during the pour, cracking at the column junction, bearing plinth levels out of tolerance.
Quality assurance
Bracket design check, plinth survey, tendon stressing records.
Examples
Standard on the game's hammerhead piers under I-girder approaches.
Related methods
Further reading
PCI Bridge Design Manual · AASHTO LRFD 5