Also called: jointless bridge, integral bridge, semi-integral abutment
How it is done
- Drive a single row of steel H-piles (weak axis) or small-diameter piles in a sleeved trench to allow movement.
- Cast the abutment stem and the deck end in one pour, embedding the girders.
- Backfill with compressible or elastic material behind the wall; provide a long approach slab sliding on the fill.
Where it fits
- Bridges up to about 60-120 m long and 30 degrees skew, moderate climates, steel or concrete girders.
Where it does not
- Long bridges with large thermal movement, high skews, very stiff foundations that cannot flex.
Plant, pace and money
PlantPiling rig, formwork, standard concrete plant.
ProductivitySimpler and faster than seat abutments.
Cost5-15 % cheaper to build and much cheaper to maintain.
Risks and controls
What goes wrong
- Ratcheting of backfill pressures over years, cracking at the deck-abutment junction, approach slab settlement.
Quality assurance
Pile orientation and flexibility checked, junction reinforcement detail inspected.
Examples
Standard in the UK, Sweden and much of the US for short bridges; the game bonus for jointless short bridges reflects it.
Related methods
Further reading
PD 6694-1 (UK integral bridges) · FHWA integral abutment guidance