Also called: strip seal, modular joint, finger joint, asphaltic plug joint, jointless design
How it is done
- Block out the deck ends to the joint detail; set the joint assembly level with the pavement, with the gap pre-set for temperature.
- Anchor into the deck and backwall concrete, cast the nosing, seal; install drainage under the joint.
- Modular joints: install as a unit with support bars and control springs; check the seal and the bearings of the bars.
Where it fits
- Bridges over 60-100 m, or shorter ones with high skew or curvature; joint type by movement range.
Where it does not
- Joints over piers and bearings without drainage (every leak corrodes the bearing below); modular joints where a series of strip seals would do.
Plant, pace and money
PlantSaws and breakers for the blockout, small crane for modular units.
ProductivityA joint in two to five days.
CostStrip seal USD 1,500-3,000 per metre; modular USD 8,000-20,000 per metre; the game's upkeep score penalises modular and finger joints most.
Risks and controls
What goes wrong
- Snowplough and truck impact damage, seal failure, noise complaints, fatigue of modular joint bars.
Quality assurance
Gap setting recorded with temperature, water test of the seal, drainage inspection.
Examples
Every seat abutment in the game; integral bridges avoid them entirely.
Related methods
Further reading
AASHTO LRFD 14.5 · NCHRP Report 467 · EN 1990 Annex A2 movements