Construction methods · Cast-in-place concrete decks
Full staging method (ground falsework)
Formwork supported on scaffold towers or a timber and steel falsework grid built up from the ground; the deck is cast in place span by span or all at once. Cheapest for short bridges over dry, firm ground with no traffic below, and the origin of every other cast-in-place method.
Also called: FSM, falsework, conventional cast-in-place, scaffold construction
Concept diagram (TheBridgeEng)
How it is done
Prepare the ground: compact, blind with concrete or sleepers, or drive short piles if soft.
Erect proprietary towers or heavy-duty props with a grid of steel beams; set the soffit formwork to the design camber including falsework settlement.
Fix reinforcement and tendons, pour in a planned sequence (midspans before supports for continuous decks), cure, stress, then strike from midspan outward.
Preload or pre-compress falsework on soft ground; monitor settlement during the pour.
Where it fits
Spans 10-50 m, deck height under about 15 m, dry ground, overpasses closed to traffic below, culvert-type crossings, short valley viaducts.
Where it does not
Water (the game's crane_ground and falsework checks), live roads and railways below, soft clay under towers, tall decks.
Plant, pace and money
PlantFalsework towers or props, steel beams, formwork, concrete pump, mobile crane.
Productivity30-45 days per span for the full cycle; faster with two sets of falsework.
CostFormwork and falsework USD 150-300 per m2 of deck; total deck USD 900-1,600 per m2.
Risks and controls
What goes wrong
Falsework collapse during the pour is the leading cause of fatalities in concrete bridge construction; settlement of tower foundations; premature striking.
Quality assurance
Independent temporary works design and check, foundation bearing verification, pre-pour inspection with a hold point, settlement monitoring during pouring.
Examples
Most short concrete overpasses; in the game it is the default for short dry spans and is barred in water and over rail.
In the bridge game
What Bridge Master applies when you pick it
Deck types: RC slab, Voided slab, RC T-beam, RC box, PSC box (cast in place), Rigid frame, Concrete arch, PSC box, balanced cantilever, Extradosed, Network tied arch. Spans 10-50 m, up to 70 m.
+25: Dry firm ground, low deck: falsework is the cheap answer.
-50: No falsework in water.
-50: No falsework over track.
-40: No falsework over live lanes unless the road can close.
-30: Tall towers get expensive and unstable.
-20: Falsework foundations settle on soft ground.
-15: Long viaduct: MSS or precast is faster.
not allowed: Ground falsework in a river.
not allowed: Ground falsework over a live railway.