Also called: temporary works design, falsework check, temporary works coordinator
How it is done
- Appoint a temporary works coordinator; register every temporary structure with a design and an independent check.
- Design for wet concrete, construction live load, wind, lateral loads (2.5 % of vertical minimum), pump surge and foundation settlement.
- Inspect before loading with a permit to load; monitor during the pour; strike only on the engineer's release after strength tests.
Where it fits
- Every project with formwork, falsework, cofferdams, travellers, gantries or trestles.
Where it does not
- Treating the supplier's catalogue as a design; loading before the permit.
Plant, pace and money
PlantNone; it is procedure and engineering.
ProductivityAdds days of engineering, saves lives.
Cost1-3 % of temporary works cost.
Risks and controls
What goes wrong
- The collapse of falsework, cofferdams and gantries: Willow Island (1978), Injaka (1998), several MSS collapses since 2000.
Quality assurance
Design and check certificates, permit-to-load records, striking release records.
Examples
BS 5975 in the UK codifies the whole procedure.
Related methods
Further reading
BS 5975 · ASCE 37 · Temporary Works Forum guidance