Also called: piled falsework, trestle falsework, falsework in water
How it is done
- Drive temporary steel pipe or H piles in bents under the falsework beams; brace them against current and debris.
- Set the falsework beams and soffit on the bents above the flood-season water level; the rest as for ground falsework.
- Strike and extract the piles before the wet season.
Where it fits
- Slow rivers and canals up to about 3 m deep, spans 20-45 m, dry-season programmes.
Where it does not
- Water beyond 3-5 m, velocities over 2 m/s, navigable routes, flood seasons.
Plant, pace and money
PlantPiling rig or barge with vibro-hammer, temporary piles, falsework, formwork.
ProductivitySlower than ground falsework: allow 45-60 days per span.
CostAdds USD 100-250 per m2 for the piles and bracing.
Risks and controls
What goes wrong
- Flood taking the falsework, debris loading, scour of the temporary piles, boat impact.
Quality assurance
Flood watch and evacuation plan, pile driving records, bracing inspection.
Examples
Small river bridges in Korea, Japan and Europe until the 1980s; still used for canals and irrigation crossings.
In the bridge game
What Bridge Master applies when you pick it
Deck types: RC slab, Voided slab, RC T-beam, RC box, PSC box (cast in place), Rigid frame, Concrete arch, PSC box, balanced cantilever, Extradosed, Network tied arch. Spans 20-45 m, up to 60 m.
- +25: Shallow, slow water: piled falsework is the cheap answer.
- -40: Too deep for piled falsework.
- -30: Fast water loads the temporary piles and debris piles up.
- -15: Only in the dry season; the falsework must be out before the floods.
- -30: Blocks the navigation route.
- not allowed: Piled falsework in 5 m+ of water is not a temporary works design, it is a bridge.
Try it in the game →