Also called: mechanically stabilised earth abutment, reinforced earth, GRS abutment
How it is done
- Cast a levelling pad; erect facing panels row by row, placing and compacting select granular fill in 300-400 mm layers with the reinforcement between.
- Build the seat beam on the fill (true abutment) or drive piles through a sleeve before the fill and cast the seat on them (mixed abutment).
- Place the approach slab and drainage.
Where it fits
- Fills of 4-15 m on competent ground, highway interchanges, sites where formwork and cranes are scarce, seismic regions (ductile).
Where it does not
- Soft foundation soils without treatment, aggressive or saline fill (corrosion of steel strips), scour-exposed river banks.
Plant, pace and money
PlantSmall crane or excavator for panels, compaction plant, no formwork.
Productivity1-2 m of wall height per day.
CostUSD 250-450 per m2 of face, roughly half of a concrete wall.
Risks and controls
What goes wrong
- Fill of the wrong grading, corrosion of reinforcement in wet or saline fill, panel bulging from poor compaction, seat settlement on a true MSE abutment.
Quality assurance
Fill grading and electrochemical tests, compaction tests per layer, panel alignment survey.
Examples
Highway interchanges worldwide since the 1970s; Gulf highways use them almost exclusively.
Related methods
Further reading
FHWA GEC 11 (MSE walls) · AASHTO LRFD 11.10 · BS 8006