Also called: composite deck slab, precast deck panels, stay-in-place formwork, full-depth precast deck
How it is done
- Cast-in-place: set forms between girders (timber, steel stay-in-place or precast panels), fix two mats of reinforcement, pour with a finishing machine, cure for seven days wet.
- Partial-depth panels: precast 80-100 mm panels span between girders as forms and bottom reinforcement; top mat and topping cast on site.
- Full-depth panels: precast full-thickness panels with shear pockets set on the girders, longitudinal PT, pockets grouted; deck done in days.
Where it fits
- All girder bridges; full-depth panels for accelerated construction and deck replacement.
Where it does not
- Cast-in-place in freezing or very hot weather without protection; full-depth panels on girders with uncontrolled camber.
Plant, pace and money
PlantFormwork, finishing machine, curing, cranes for panels.
ProductivityCast-in-place 2-3 weeks per span; full-depth panels a few days.
CostCast-in-place USD 150-250 per m2; full-depth precast USD 300-450 per m2.
Risks and controls
What goes wrong
- Early cracking from shrinkage and restraint, low cover over the top mat, panel seating gaps.
Quality assurance
Cover surveys, curing records, panel haunch grouting, crack mapping at 28 days.
Examples
Full-depth panels are standard for US deck replacements and Korean ABC.
Related methods
Further reading
PCI Full-Depth Deck Panel Guidelines · FHWA ABC Manual