Also called: crane placement, girder erection by crane, tandem lift
How it is done
- Cast girders in a yard (30-50 m, 40-120 t); transport by truck or barge; stage at the site.
- Position the crane on firm ground at each span; lift each girder to the bearings, brace it laterally at once (girders are unstable alone), repeat across the width.
- Place diaphragms and precast or cast-in-place deck slab; the slab makes the girders composite.
Where it fits
- Overpasses, viaduct approaches, river bridges from the banks or a trestle, spans to about 45-50 m (55 m with two cranes), any site with crane access on both sides.
Where it does not
- Piers in water without a trestle or barge, heights over 30-40 m (crane capacity falls with radius), sites where girder transport cannot reach.
Plant, pace and money
PlantCrawler crane 250-600 t (or two), transport, bracing, deck formwork.
ProductivityOne to three days per span; a girder every 30-60 minutes once set up.
CostDeck USD 800-1,300 per m2; among the cheapest.
Risks and controls
What goes wrong
- Girder rollover before bracing (a recurring fatal accident), crane tipping on soft ground, lifting in wind, crane outriggers on the edge of an excavation.
Quality assurance
Lift plan for each span with ground bearing checks, bracing installed before the crane releases, girder camber checked before placing the slab.
Examples
The game's default approach-span method; most Korean, US and European highway bridges.
In the bridge game
What Bridge Master applies when you pick it
Deck types: PSC I-girder, PSC U-girder, Voided slab, Spliced PSC girder, Timber deck, FRP deck, Precast segmental box, RC slab, Steel plate girder, Steel box girder. Spans 15-45 m, up to 60 m.
- +25: Cranes can stand at the piers: just lift them in.
- +15: Night lifts from the verge or in a possession.
- -40: Cranes cannot stand in water; launcher or barge.
- -30: No crane positions; use a launching girder.
- -25: Tall piers exceed reach; launcher.
- -20: Very heavy girders need large tandem cranes.
- not allowed: Land crane erection over deep water.