Also called: treated timber piling, wood piles
How it is done
- Select straight, seasoned logs 250-400 mm at the butt; treat with preservative.
- Drive with a light hammer and a driving ring to protect the head; avoid overdriving.
- Cut off below the permanent water level or protect the head with a cap.
Where it fits
- Temporary trestles and falsework, small rural bridges, historic replacements, soft ground with 100-400 kN per pile.
Where it does not
- Any exposure above the water table without treatment; marine borers; hard driving.
Plant, pace and money
PlantLight crawler rig or crane-hung hammer.
Productivity15-30 piles per shift.
CostUSD 30-80 per metre.
Risks and controls
What goes wrong
- Brooming of the head, decay at the water line, borer attack in the sea.
Quality assurance
Straightness and treatment certificates, driving records.
Examples
Temporary trestles for river bridges worldwide; Venetian foundations are the famous permanent case.
Related methods
Further reading
ASTM D25 · AWPA standards