Also called: span-by-span erection, overhead gantry, underslung gantry, segmental viaduct
overhead gantry segments hung, epoxied, stressed into one span 2-4 days per span Span-by-span precast segmental Concept diagram (TheBridgeEng)
How it is done Cast segments short-line in a yard (one segment per cell per day), store, deliver by truck or along the deck. Hang all segments of the span from the gantry on temporary bars, align, apply epoxy, close with temporary PT. Thread and stress the external or internal tendons, set the span on bearings, launch the gantry.
Where it fits Viaducts with 30-50 m spans and more than 15-20 spans, urban and marine settings, metros, tight sites with only overhead access. Where it does not Few spans, varying spans, spans over 50-55 m (weight), sharp curves for overhead gantries.
Plant, pace and money Plant Gantry 80-120 m, 300-600 t; casting yard with short-line cells; segment transport.
Productivity One span per two to four days per gantry.
Cost Deck USD 1,300-1,900 per m2 including yard and gantry over a long viaduct.
Risks and controls What goes wrong Gantry collapse during launching (several accidents), epoxy joint failure, geometry error accumulating across segments, temporary bar failure. Quality assurance Match-cast geometry control in the yard, epoxy application in temperature limits, stressing records, gantry launch procedure.
Examples Dubai Metro, Bangkok, Hong Kong-Zhuhai-Macau approaches, Sheikh Zayed Bridge approaches, many US urban viaducts.
In the bridge game What Bridge Master applies when you pick it Deck types: Precast segmental box, PSC box (cast in place), PSC I-girder, PSC U-girder, Voided slab. Spans 30-50 m, up to 60 m.
+35: Kilometres of 30-55 m spans: gantry span-by-span. +15: Marine or urban viaduct with no ground access. -40: Gantry and yard cannot be amortised. -40: Beyond span-by-span. -20: Gantry geometry on tight curves is awkward. not allowed: Span-by-span gantry beyond feasibility. Try it in the game →
Related methods
Further reading ASBI Construction Practices Handbook · AASHTO Guide Specifications for Segmental Bridges