Also called: floated-in cofferdam, precast concrete cofferdam, steel box cofferdam
How it is done
- Fabricate the box in a dry dock or on a slipway; tow it to the pier.
- Lower it over the pile group on strand jacks or by ballasting, seat it on brackets welded to the piles or on a prepared bed.
- Seal the pile penetrations with grout collars or a tremie plug, dewater, and cast the cap inside; the box becomes lost formwork.
Where it fits
- Sea and estuary piers with pile groups in 8-25 m of water, where sheet piles cannot be driven or would take too long.
Where it does not
- Sites without a fabrication yard or towing route; small piers where a sheet-pile cofferdam is cheaper.
Plant, pace and money
PlantYard, tugs, strand jacks or ballast systems, survey for setting.
ProductivityOne box every few weeks from a yard; setting in one or two tidal windows.
CostUSD 1-4 million per box, offset by faster caps.
Risks and controls
What goes wrong
- Towing and setting in weather windows; seal failure at pile penetrations.
Quality assurance
Leak test after seating, level and position survey, grout collar inspection.
Examples
Hong Kong-Zhuhai-Macau, Incheon Bridge and many Gulf sea bridges used precast cap shells; the game's high pile cap uses this rate.
Related methods
Further reading
fib Bulletin on marine foundations · project papers on HZMB and Incheon Bridge