Also called: well foundation, open well, sunk caisson
How it is done
- Build a sand island or a staging in shallow water; cast the first lift with the cutting edge and pump wells or dredge pockets.
- Excavate inside with grabs or airlifts; the caisson sinks; add lifts as it goes; kentledge or water ballast helps in stiff layers; jetting and lubricating with bentonite reduce skin friction.
- At founding level, clean and plug the base with tremie concrete, fill the wells with sand or concrete, cast the cap.
Where it fits
- Rivers with deep scour (10-20 m), navigable rivers with ship impact, ground where piles would need to be very long, cohesionless beds that dredge easily.
Where it does not
- Boulder beds and rock where the cutting edge stops (divers or pneumatic work needed), sites where tilt during sinking cannot be tolerated.
Plant, pace and money
PlantGrabs and cranes, airlifts, concrete supply, jetting pumps, survey for tilt and shift.
ProductivitySinking 0.3-1.5 m per day; a 40 m caisson takes months.
CostUSD 5-30 million per major pier; competitive only where scour and depth rule out piles.
Risks and controls
What goes wrong
- Tilting and shifting during sinking (the classic failure), sand blows and sudden drops, cutting edge damage, base blow-in when dewatered.
Quality assurance
Tilt and position surveyed every shift, excavation kept balanced, dredging logs, base inspection by divers before the plug.
Examples
Howrah (Kolkata) and Mahatma Gandhi Setu, Jiangyin and Yangtze crossings, older Mississippi bridges; the game offers it for big water piers.
Related methods
Further reading
IRC 78 (India) · Chinese JTG D63 · Peck, Hanson and Thornburn