Also called: settlement monitoring, piezometers, inclinometers, structural health monitoring
How it is done
- Install instruments before the load is applied: settlement plates and piezometers under approach fills, inclinometers beside cofferdams and deep excavations.
- Set trigger levels (green, amber, red) tied to specific actions.
- Read and plot at a frequency matching the rate of change; report against the predicted curves.
- On cantilever and cable-stayed decks, survey the geometry every segment and adjust the next one.
Where it fits
- Soft-ground approaches, deep excavations, balanced cantilever and stayed construction, launching.
Where it does not
- Installing instruments without a plan for what to do when a trigger is reached.
Plant, pace and money
PlantInstruments, data loggers, survey total stations, sometimes automated systems.
ProductivityContinuous.
Cost0.5-2 % of the works it protects.
Risks and controls
What goes wrong
- Damaged instruments during earthworks; data that nobody reads.
Quality assurance
Named person responsible for readings and for the trigger response; weekly plots in the progress meeting.
Examples
PVD-treated approaches are released for pavement only when settlement plates show the predicted consolidation; cantilever decks are cambered from survey data segment by segment.
Related methods
Further reading
Dunnicliff, Geotechnical Instrumentation for Monitoring Field Performance