Also called: incremental launching method, push-launch, ILM
How it is done
- Build the casting bed and the launching abutment; install sliding bearings with PTFE pads on every pier.
- Cast a segment on the bed (one to two weeks), stress the centric launching tendons, launch by jacks (lift-and-push or friction launchers) at 5-10 m per hour.
- Repeat until the deck is in place; then install permanent bearings, add the continuity tendons, remove the nose.
Where it fits
- Straight or constant-curvature alignments, constant depth box girders, spans 30-60 m (up to 100 m with temporary piers), sites with no access under the deck: valleys, rivers, railways, environmentally protected ground.
Where it does not
- Variable alignments and spans, very long spans without temporary piers, decks that cannot be constant depth.
Plant, pace and money
PlantCasting bed with formwork, launching jacks or friction launchers, launching nose (0.6 span long), temporary sliding bearings, lateral guides.
ProductivityOne segment per 7-14 days; 20-30 m of bridge per cycle.
CostDeck USD 1,300-2,000 per m2; the bed and nose USD 1.5-4 million.
Risks and controls
What goes wrong
- Nose landing on the pier misaligned, friction and pier deflection during launching, overstress of the deck as it passes the pier (every section becomes a support section), unbalanced friction pulling the deck sideways.
Quality assurance
Launch procedure with pier deflection monitoring, bearing friction checks, survey of the nose landing, tendon stressing records.
Examples
Rio-Caroni (the first), Millau Viaduct (steel), hundreds of European and Korean valley and railway crossings.
In the bridge game
What Bridge Master applies when you pick it
Deck types: PSC box (cast in place), RC box, PSC box, balanced cantilever. Spans 30-50 m, up to 65 m.
- +30: Straight, repetitive, no ground access: ILM.
- +20: Launching over rail needs no possession except for the nose passage.
- +15: Nothing in the river during construction.
- -45: Variable curvature cannot be launched.
- -35: Launching moments too high; temporary piers or another method.
- -30: Too short to set up a casting bed.
- +5: Tall piers: launching avoids tall falsework, but pier top forces need checking.
- not allowed: ILM on a variable-radius alignment.
Try it in the game →
Related methods
Further reading
Rosignoli, Bridge Launching · SETRA guide on incremental launching