Also called: high-strain dynamic test, PDA, CAPWAP
How it is done
- Bolt transducers to the pile 1.5-2 diameters below the head.
- Strike with the driving hammer (driven piles) or a drop weight of 1-2 % of the test load (bored piles).
- Record force and velocity, run signal matching, report capacity, driving stresses and hammer energy.
Where it fits
- Driven piles at end of drive and restrike (setup, relaxation), bored piles in numbers, quality control across a site.
Where it does not
- Using it as the only capacity proof for large or unusual piles.
Plant, pace and money
PlantPDA unit, transducers, drop hammer or the piling hammer.
ProductivitySeveral piles per day.
CostUSD 2,000-8,000 per test.
Risks and controls
What goes wrong
- Insufficient hammer energy to mobilise the base; results then underestimate capacity.
- Restrike timing: too early misses setup.
Quality assurance
Correlate with at least one static test per pile type; report hammer energy and mobilised set for each blow.
Examples
Routine on PHC and steel pipe pile projects in Korea, Japan and the Gulf.
Related methods
Further reading
ASTM D4945 · ISO 22477-10