Construction methods · Ground improvement

Dynamic compaction

A 10-25 t weight dropped from 15-25 m on a grid densifies loose granular fill and rubble to 8-12 m. Crude, fast and cheap where there is space and no neighbours.

How bridges get built · Ground improvement · Dynamic compaction

Also called: heavy tamping, dynamic consolidation

How it is done

  1. Drop the weight several times at each grid point in two or three passes with decreasing spacing; a final ironing pass with low drops levels the surface.
  2. Monitor crater depth and surface settlement; test with CPT or SPT between passes.

Where it fits

  • Loose sand and gravel fill, rubble, reclaimed land, old industrial sites under approaches.
  • Depths to about 10 m.

Where it does not

  • Saturated clays and silts (no densification, only pore pressure).
  • Within 30-50 m of structures or services sensitive to vibration.

Plant, pace and money

PlantLarge crawler crane (100-200 t) with a free-fall drum and a tamper.
Productivity2,000-5,000 m2 per crane per week.
CostUSD 8-20 per m2.

Risks and controls

What goes wrong

  • Vibration damage, flying debris, crane fatigue.

Quality assurance

Pre- and post-CPT, plate load tests, vibration monitoring at the site boundary.

Examples

Airport and port fills; occasionally bridge approaches on rubble fill.