Also called: deck jacking, bridge raising, bearing jacking, synchronised lifting
How it is done
- Design jacking points on the pier or on temporary brackets; check the deck for the new support conditions.
- Install jacks with load cells and mechanical locks; lift in small steps with synchronised control, monitoring the deck for differential movement.
- Do the work (bearing change, plinth raising), then lower in steps onto the new support.
Where it fits
- Bearing replacement, clearance increases, ILM and slide landing, settlement correction.
Where it does not
- Jacking without locks (hydraulic failure drops the deck); jacking a continuous deck at one pier without checking the others.
Plant, pace and money
PlantHydraulic jacks (50-1,000 t), synchronised pumps, load cells, locking rings, brackets.
ProductivityA pier in a day.
CostUSD 20,000-200,000 per pier.
Risks and controls
What goes wrong
- Differential lift cracking the deck, jack slippage, bracket failure.
Quality assurance
Jacking procedure with limits per step, load and displacement logs, survey of the deck during the lift.
Examples
Bearing replacements on every ageing viaduct; raising of Sydney and Bayonne-type bridges for shipping clearance.
Related methods
Further reading
Enerpac synchronised lifting guides · AASHTO Manual for Bridge Evaluation