Also called: barrette pile, rectangular bored pile, diaphragm wall panel foundation
rock grab or hydromill panel 0.8-1.5 x 2.8-7 m under bentonite guide walls T, L, cross Barrette (rectangular bored pile) Concept diagram (TheBridgeEng)
How it is done Build guide walls; excavate the panel under bentonite slurry with a cable-hung grab or a hydromill in rock. Clean the trench, desand the slurry, lower the cage (often in sections with couplers), tremie the concrete. Panels can be T-, L- or cross-shaped for bending in both directions.
Where it fits Pylon foundations, high piers with large moments, sites with obstructions where the hydromill cuts through, deep foundations to 80 m. Where it does not Small loads, sites where a few round piles would do, ground with cavities that swallow slurry.
Plant, pace and money Plant Diaphragm wall grab or hydromill on a crawler crane, slurry plant with desanding, large cranes for cages.
Productivity One 3 x 1.2 m panel of 40 m in three to six days.
Cost USD 500-1,000 per m2 of panel face; competitive with 2-3 m shafts for large moments.
Risks and controls What goes wrong Trench collapse with slurry loss, panel joint quality, cage cover in a rectangular section. Quality assurance Slurry testing, trench verticality by Koden sonic survey, CSL tubes, O-cell test.
Examples Pylons of several Chinese and Middle Eastern cable-stayed bridges; tall urban viaduct piers in Hong Kong.
Related methods
Further reading EN 1538 (diaphragm walls) · Xanthakos, Slurry Walls