A rectangular pile excavated with a diaphragm-wall grab or hydromill under bentonite, typically 0.8-1.5 m by 2.8-7 m, giving very high axial and bending capacity in one element. Used under pylons and tall piers where round shafts would be too many or too large.

How bridges get built · Bored piles and deep foundations · Barrettes and diaphragm-wall foundations

Also called: barrette pile, rectangular bored pile, diaphragm wall panel foundation

rockgrab or hydromillpanel 0.8-1.5 x 2.8-7 m under bentoniteguide wallsT, L, crossBarrette (rectangular bored pile)
Concept diagram (TheBridgeEng)

How it is done

  1. Build guide walls; excavate the panel under bentonite slurry with a cable-hung grab or a hydromill in rock.
  2. Clean the trench, desand the slurry, lower the cage (often in sections with couplers), tremie the concrete.
  3. Panels can be T-, L- or cross-shaped for bending in both directions.

Where it fits

  • Pylon foundations, high piers with large moments, sites with obstructions where the hydromill cuts through, deep foundations to 80 m.

Where it does not

  • Small loads, sites where a few round piles would do, ground with cavities that swallow slurry.

Plant, pace and money

PlantDiaphragm wall grab or hydromill on a crawler crane, slurry plant with desanding, large cranes for cages.
ProductivityOne 3 x 1.2 m panel of 40 m in three to six days.
CostUSD 500-1,000 per m2 of panel face; competitive with 2-3 m shafts for large moments.

Risks and controls

What goes wrong

  • Trench collapse with slurry loss, panel joint quality, cage cover in a rectangular section.

Quality assurance

Slurry testing, trench verticality by Koden sonic survey, CSL tubes, O-cell test.

Examples

Pylons of several Chinese and Middle Eastern cable-stayed bridges; tall urban viaduct piers in Hong Kong.

Related methods

Further reading

EN 1538 (diaphragm walls) · Xanthakos, Slurry Walls