Suspension Bridge Records · United States

Carquinez Bridge (Alfred Zampa Memorial Bridge)

A 728 m main span over the Carquinez Strait in California, opened in 2003: the first suspension bridge in the United States with an orthotropic steel box deck.

Suspension Bridge Records · United States

Carquinez Bridge (Al Zampa): How It Was Built

A 728 m main span over the Carquinez Strait in California, opened in 2003: the first suspension bridge in the United States with an orthotropic steel box deck.

The Alfred Zampa Memorial Bridge carries westbound Interstate 80 over the Carquinez Strait between Vallejo and Crockett, beside the 1958 cantilever bridge that carries the eastbound traffic. It replaced the 1927 cantilever bridge, which was demolished by 2007, and it is named after Al Zampa, an ironworker who worked on many Bay Area bridges.

It was the first major suspension bridge built in the United States since 1973, the first new suspension bridge in the Bay Area since the Golden Gate, and the first suspension bridge in the country with an orthotropic steel box deck. The deck carries three traffic lanes, a carpool lane, two shoulders and a path for cyclists and walkers on the side facing San Pablo Bay.

Carquinez Bridge (Al Zampa)
The Alfred Zampa Memorial Bridge, the 2003 Carquinez suspension bridge. Photo: Kevin Collins, CC BY 2.0, via Wikimedia Commons

Key facts

LocationCarquinez Strait on Interstate 80, between Crockett (Contra Costa County) and Vallejo (Solano County), California
TypeSuspension bridge with a closed orthotropic steel box girder; earth-anchored
Spans147 + 728 + 181 m
Main span728 m
TowersReinforced concrete portal frames, 128 m (north) and 123 m (south), hollow legs, jump-formed
DeckClosed orthotropic steel box girder, 29 m wide and 3 m deep, continuous between the north anchorage and the south transition pier
Main cable2 cables, each 8,584 galvanised wires of 1,570 MPa minimum in 37 strands, compacted to 512 mm
Cable erectionAerial spinning (controlled tension)
HangersPairs of galvanised wire ropes with resin sockets at each panel point, 12.4 m apart
Built2000 to 2003; dedicated 8 November 2003; opened 11 November 2003
OwnerCalifornia Department of Transportation (Caltrans)
DesignDe Leuw, OPAC and Steinman joint venture, with Caltrans
ConstructionFCI Constructors and Cleveland Bridge California joint venture; deck by IHI (Japan); erection engineering by DLT Engineering; cable spinning managed by Dorman Long Hordaland; wire by Bridon
CostAbout US$240 million

Design

The design was finalised by the De Leuw, OPAC and Steinman joint venture with Caltrans, and drew on the seismic lessons of recent earthquakes in California and elsewhere. The two reinforced concrete towers have hollow legs and two post-tensioned struts designed to stay elastic in an earthquake.

The deck is a single orthotropic steel box, a relatively light, stiff and aerodynamic section in which most welded and bolted connections are enclosed and protected, with room inside for maintenance access and utilities. It is continuous over its whole length, with only two expansion joints, one at each end of the bridge. The steel deck is paved with a thin two-layer Trinidad Lake Asphalt over a waterproof membrane.

How it was built

Foundations

Each tower leg stands on six drilled shafts 3 m in diameter, 12 per tower. Steel casings were driven to bedrock, about 155 ft (47 m) on the south side and 127 ft (39 m) on the north, with rock sockets of about 141 ft and 79 ft beyond. The fractured rock on the south side was drilled in 25 ft stages, filled with lean concrete and re-cored. The pile caps were cast inside precast concrete shells, which were floated into position at high tide and lowered onto the shafts as the tide fell, while traffic stayed on the 1927 bridge alongside. The south anchorage sits on fill over soft clay and loose sand and is founded on 380 steel-cased piles 30 in. in diameter; the north anchorage bears directly on rock.

Towers

The towers rise about 410 ft above the water and were built by jump forming.

Cables

The main cables were aerially spun under controlled tension, a method chosen by the contractor. Each holds 8,584 zinc-coated wires of 228 ksi (1,570 MPa) minimum strength, splays into 37 strands at the gravity anchorages and was compacted to 20.2 in. (512 mm). Once the cable carried the whole weight of the bridge, it was coated with zinc paste, wrapped tightly with 3.5 mm galvanised wire and given three coats of paint.

Deck from Japan

The deck was fabricated by IHI in Nagoya and test fitted in Japan before shipping. It was erected in 24 units instead of the 48 specified, saving about US$1 million in site welding; typical units were 50 m long, 29 m wide and about 600 t. Three ships, each carrying eight units, made the three-week crossing of the Pacific; the first left Nagoya on 4 January 2003 and arrived on 24 January.

The large units and the nearby 1927 bridge ruled out the usual lifting gantry. Instead, four strand jacks were mounted on each deck unit and their strands were hung from the main cables by large temporary cast steel cable bands, so each unit lifted itself; a lift, including transfer to the permanent suspenders, took about four hours. About half the units were lifted straight up from the ships. In mid-strait, piers of the existing bridges blocked the water below, so units were raised as close as possible and swung into place with extra strand jacks and cable bands, one by more than 50 m. On the Vallejo side the water was too shallow, so units were lowered onto barges, taken between the bluffs and the north tower, raised and moved into position on walking hydraulic jacks; on the Crockett side a temporary trestle blocked access, so units were swung through the tower legs with inches to spare and landed on the trestle. The deck erection alone cost about US$17.2 million. The units were then bolted and welded into one continuous girder.

Key dates

2000Construction begins
4 January 2003First ship with eight deck units leaves Nagoya
24 January 2003First deck units arrive in the Bay Area
8 November 2003Bridge dedicated
11 November 2003Opened to traffic
4 September 2007Demolition of the 1927 bridge complete

What engineers remember it for

  • The first suspension bridge in the United States with an orthotropic steel box deck.
  • Deck units lifted by strand jacks mounted on the units themselves, hung from temporary cable bands, instead of a gantry.
  • The first major US suspension bridge since 1973.

Construction records

The construction records below can be read in the browser or downloaded. Large scanned volumes may take a moment to open.

Carquinez BridgePDF · 45 MB
PreviewDownload
Carquinez Bridge: steel deckPDF · 8.4 MB
PreviewDownload

← All suspension bridge records

Questions engineers ask

How was the Carquinez Bridge deck erected?
In 24 steel box units of about 600 t, shipped from Japan. Four strand jacks on each unit, hung from the main cables by temporary cable bands, lifted it into place in about four hours; units that ships could not reach were swung or skidded into position.
How were the Carquinez Bridge cables built?
By aerial spinning under controlled tension: 8,584 wires of 1,570 MPa per cable in 37 strands, compacted to 512 mm and wrapped with galvanised wire over zinc paste.

Sources

Updated 2026-11-13 · written by a practising bridge engineer