Budhi Gandaki flood bridges (Arughat, Soti, Machhakhola–Kerauja and others) (2026)

Nepal · Flood / debris · Group of crossings: suspension footbridges (Nyakchet–Sirdibas, Machhakhola–Kerauja and others), a motorable steel bridge at Soti, the Gorkha–Dhading bridge at Arughat and a Bailey bridge in Dharche

Early on Sunday 11 October a sudden surge came down the upper Budhi Gandaki in Gorkha.…

Read the full case — mechanism, cause chain, code changes →

More Flood / debris cases

Kampung Brooke Lama suspension bridge (Jambatan gantung Kampung Brooke Lama) (2026) · Talitay hanging bridge (2026) · Ban Had Ngio suspension bridge (สะพานแขวนบ้านหาดงิ้ว) (2026) · Trishuli / Bhote Koshi valley bridges (Langtang Lirung glacier collapse) (2026) · FM 481 Nueces River Bridge (2026) · Sataso Bridge (Mampong–Ejura road) (2026)