Albert Bridge, the pink-and-white Victorian crossing linking Chelsea and Battersea over the Thames, has been closed to motor traffic since early February 2026. The closure took effect on 7 February 2026 after a routine inspection found a cracked cast-iron component at one of the bridge abutments. The 150-year-old crossing opened in 1873, is Grade II* listed, and is one of only two London bridges never to have been replaced, alongside Tower Bridge. It was nicknamed "The Trembling Lady" soon after opening because it is designed to move slightly with temperature, wind, and traffic.
The investigation found that the cracked cast-iron component supports a joint between the catenary, cable-stay, and edge girder. That joint is meant to rock as conditions change, and the damage occurred when the axle within it seized.
On 25 March 2026, the council's leadership team decided on a full repair rather than a quick temporary fix, which experts advised was unlikely given the bridge's fragility and complexity. The plan is to repair the cracked component, free the seized axle, and add preventative measures to stop parts seizing again, along with a new road surface, refurbished toll booths, and earlier replacement of the lighting.
The works are valued at about £8.5 million and are expected to take around 12 months, keeping the bridge shut to cars into 2027.
In April 2026 a temporary support prop was installed to hold the weakened cast-iron component and reduce the risk of also having to close the bridge to pedestrians and cyclists. The bridge remains open to pedestrians and cyclists and is being monitored by sensors that model its movements, supported by ultrasonic scanning and inspection of submerged parts. A 3-tonne weight limit had been in force since January 2024, with cameras issuing fines to overweight vehicles, and this fault was found during the stepped-up inspections that followed.
The case echoes Hammersmith Bridge, which has been closed to road traffic since 2019 over cracking in its cast-iron plinths, where remediation costs have soared and the problem remains unresolved. The council's lead member for planning and environment stressed that the bridge is a national landmark and a vital river crossing, and that the aim is to reopen it and protect it for the future.